Atommash has carried out a check assembly of Reactor vessel for Kudankulam NPP

Atommash
Фотоматериалы
Reactor
Kudankulam
26.01.2023

Atommash Branch, AEM-Technologies, JSC in Volgodonsk (a part of machine-building division of Rosatom –Atomenergomash) has performed an assembly of the Reactor vessel with the Internals. The item is being manufactured for power unit No. 5 of NPP "Kudankulam" (India).

Check assembly was carried out in an underground caisson. First, using a crane with a lifting capacity of 600 tons, the specialists installed the 11-meter VVER-1000 Reactor Vessel on its design position. Then, one after another, they lowered the 10-meter long Core Barrel weighing 73 tons, the Core Baffle weighing 38 tons, and the Protective Tube Unit weighing 68 tons. The Reactor was then closed with the standard Reactor Cover. The total assembled weight of the item reached 603 tons.

During the assembly, the staff installed keys and fasteners on the Reactor Vessel and fixed the centering device of the Reactor cover. During check assembly, the items exactly repeat their design position. In this case it significantly reduces the deadline and simplifies the mounting of the Reactor facility at the NPP construction site.

Reactor is a vertical cylindrical vessel with an elliptical bottom, there is a core and Internals inside the item. From above, the equipment is sealed with a Cover with drives of mechanisms and control and protection units installed on it, nozzles for outputting cables of in-reactor control sensors.

Building of Kudankulam NPP in Tamil Nadu in the south of India includes the construction of six power units with VVER-1000 reactors type having capacity of 6000 MW. The first stage, consisting of power units No. 1 and No. 2, was included in the national power grid of India in 2013 and 2016, respectively. At the moment, the construction of power units No. 3, 4 and No. 5, 6, which are the second and third stages of Kudankulam NPP, is being performed.

К списку новостей
Atommash has carried out a check assembly of Reactor vessel for Kudankulam NPP

Читайте также:

Atommash has shipped equipment for the Turbine generator building of Akkuyu NPP, unit No. 2
Atommash has shipped equipment for the Turbine generator building of Akkuyu NPP, unit No. 2
Atommash has shipped equipment for the Turbine generator building of Akkuyu NPP, unit No. 2
The final stage of equipment manufacturing is hydraulic test during which the Modules of tube system were set at an angle on the special support system, large plugs with the dimension of 4х6 meters were installed and fastened with studs. Then each item was filled with purified desalinated water, pressure was built up to the maximum level of 7.5 atmospheres, after that the Modules were held under the pressure for an hour. During the test, the strength and tightness of the Modules of tube system were confirmed.
Reactor pressure vessel for Xudapu NPS successfully passed hydraulic tests at Atommash
Reactor pressure vessel for Xudapu NPS successfully passed hydraulic tests at Atommash
Reactor pressure vessel for Xudapu NPS successfully passed hydraulic tests at Atommash
At AEM-Technologies Atommash hydraulic test of the reactor pressure vessel for Unit 3 of the Xudapu NPS, which is under construction in China, was successfully completed. The tests were conducted in a three-level underground caisson, a special sealed shaft designed for such work. Using a crane with a lifting capacity of 600 tons, the support ring was first lowered into the stand, and then the 11-meter VVER-1200 reactor vessel was placed on it with an accuracy of 0.5 mm. To create complete sealing, plugs and top head were used, which were connected to the reactor pressure vessel using 54 main joint studs. During the tests the item was filled with distilled water, heated to 100 degrees and created the maximum pressure (24.5 MPa) - this is 1.4 times higher than the working pressure.
Petrozavodskmash has begun to ship reactor coolant pump housings for Tianwan NPS
Petrozavodskmash has begun to ship reactor coolant pump housings for Tianwan NPS
Petrozavodskmash has begun to ship reactor coolant pump housings for Tianwan NPS
In the course of manufacture, the RCP housings are subjected to all necessary kinds of inspection, particularly radiography, and a series of tests, of which hydraulic tests under overpressure (24.5 MPa) are of key importance. Upon approval as a result of all the inspections, the equipment is ready for shipment after being paint coated and preserved. Petrozavodskmash has shipped the first RCP housing for Tianwan NPS. In total, the scope of delivery comprises four RCP housings and spacers.