AEM-Technologies, JSC has shipped tanks for safety systems to Akkuyu NPP

Ижора
Фотоматериалы
Shipments
Akkuyu
12.12.2022

AEM-Technologies Izhora (a part of machine-building division of Rosatom - Atomenergomash) has shipped passive core flooding systems tanks for Akkuyu NPP Unit 2 (Turkey).

Eight PCFS tanks were dispatched to the first nuclear power plant in Turkey that is the exact number of tanks required for operation of the system. The outside diameter of each tank is 4.2 m, the length is 11 m, and the weight is 80 t.

The route to the site runs through the Baltic Sea, the Atlantic Ocean and then the Mediterranean Sea and makes up over eight thousand kilometers.

The PCFS is an important element of the NPP safety system. In worst-case situations in the primary circuit it removes residual heat. Water solution of boron acid heated up to 60 degrees is stored in the tanks. If pressure in the primary circuit drops below a certain level, the liquid is automatically supplied to the reactor to cool down the core.

Akkuyu NPP in Turkey is the first project in the world that is implemented according to the Build-Own-Operate model. The design includes four power units with Russian reactors of VVER-type, 3+ generation with enhanced safety and improved performance characteristics. The facility is designed by engineering division of the State Atomic Energy Corporation Rosatom. The power of each unit is 1200 MW.

According to the intergovernmental agreement between the Russian Federation and the Republic of Turkey, Unit 1 of the NPP shall be commissioned within 7 years after all the permits and licenses for the Unit construction have been obtained. Considering that the license for construction of Unit 1 was obtained in 2018, the commissioning is expected to be in 2025. But the participants of the project do their best to complete the construction of Unit 1 and to ensure the readiness for commissioning test in 2023, which is an anniversary year for the Republic of Turkey.

К списку новостей
AEM-Technologies, JSC has shipped tanks for safety systems to Akkuyu NPP

Читайте также:

Atommash has shipped equipment for the Turbine generator building of Akkuyu NPP, unit No. 2
Atommash has shipped equipment for the Turbine generator building of Akkuyu NPP, unit No. 2
Atommash has shipped equipment for the Turbine generator building of Akkuyu NPP, unit No. 2
The final stage of equipment manufacturing is hydraulic test during which the Modules of tube system were set at an angle on the special support system, large plugs with the dimension of 4х6 meters were installed and fastened with studs. Then each item was filled with purified desalinated water, pressure was built up to the maximum level of 7.5 atmospheres, after that the Modules were held under the pressure for an hour. During the test, the strength and tightness of the Modules of tube system were confirmed.
Reactor pressure vessel for Xudapu NPS successfully passed hydraulic tests at Atommash
Reactor pressure vessel for Xudapu NPS successfully passed hydraulic tests at Atommash
Reactor pressure vessel for Xudapu NPS successfully passed hydraulic tests at Atommash
At AEM-Technologies Atommash hydraulic test of the reactor pressure vessel for Unit 3 of the Xudapu NPS, which is under construction in China, was successfully completed. The tests were conducted in a three-level underground caisson, a special sealed shaft designed for such work. Using a crane with a lifting capacity of 600 tons, the support ring was first lowered into the stand, and then the 11-meter VVER-1200 reactor vessel was placed on it with an accuracy of 0.5 mm. To create complete sealing, plugs and top head were used, which were connected to the reactor pressure vessel using 54 main joint studs. During the tests the item was filled with distilled water, heated to 100 degrees and created the maximum pressure (24.5 MPa) - this is 1.4 times higher than the working pressure.
Petrozavodskmash has begun to ship reactor coolant pump housings for Tianwan NPS
Petrozavodskmash has begun to ship reactor coolant pump housings for Tianwan NPS
Petrozavodskmash has begun to ship reactor coolant pump housings for Tianwan NPS
In the course of manufacture, the RCP housings are subjected to all necessary kinds of inspection, particularly radiography, and a series of tests, of which hydraulic tests under overpressure (24.5 MPa) are of key importance. Upon approval as a result of all the inspections, the equipment is ready for shipment after being paint coated and preserved. Petrozavodskmash has shipped the first RCP housing for Tianwan NPS. In total, the scope of delivery comprises four RCP housings and spacers.